If you're having trouble viewing this email, you may see it online.
Forward this message to a friend
CENTRAL BIOSOLIDS
TIMELINE
 
2006: 
Construction continues 
Summer 2007:
Begin start-up of new biosolids facility
June 2008: 
Final completion of biosolids project


Concrete poured for digesters
Concrete poured for digesters, the large cylindrical tanks that will stablize sludge and provide methane gas for drying
(July 2006)
click photo to enlarge

 
<<<<<<<<<<<<<<<<

CENTRAL ODOR CONTROL
TIMELINE

August 2006:
Start-up of new odor control facilities

 
Aluminum covers and ductwork installed
New aluminum covers and ductwork installed to capture odors for Central odor control project
(July 2006)

click photo to enlarge


<<<<<<<<<<<<<<<<

DRY CREEK FACILITY
IMPROVEMENT TIMELINE

September 2006:
Start-up of new odor control facilities
September 2007:
Start-up of new biosolids facilities
November 2007:
Final project completion

Fans and biofilter for controlling odor installed at Dry Creek Wastewater Treatment Plant
(July 2006)
click photo to enlarge
Biosolids and Odor Control Project,
August 2006 Update 

Metro Water Services (MWS) is pleased to provide this update on the status of the Biosolids and Odor Control Project. There are three separate project elements included in this effort: upgrade our Central and Dry Creek wastewater treatment facilities, protect the environment and become a better neighbor to the community.

Central Biosolids Project Update
Construction continues for the $117 million biosolids project. Concrete is being placed for the digesters, which will stabilize sludge and provide methane gas for drying (see photo). Piping and electrical conduit have been placed under the slab that serves as the foundation for the dewatering and heat drying building (see photo).

The project is on schedule for start-up activities to begin in the summer of 2007, and will complete improvements to the Central complex, allowing it to be a better neighbor to the residents of Germantown and Salemtown. The biosolids facility will require nearly a year for start-up and testing, with final completion of the project in June 2008.

For more details on construction hours and contact information, visit the biosolids project page.

Central Odor Control Project Nears Completion
The new odor control system at the Central Wastewater Treatment Plant is beginning start-up activities this month. Most recently, the construction team completed work on the new biofilter treatment system and is continuing to work to connect ductwork to the new aluminum covers to capture odors (see photo).

While this element of the overall project is critical to minimizing odor surrounding the Central Wastewater Treatment Plant, the most significant improvement will occur once the new biosolids handling facility is operational beginning in summer 2007. At that time, we will change the way we handle sludge, which is responsible for the remaining odors emanating from Central. To learn more about the current and future methods of sludge handling at Central, please visit this interactive animation on our Web site.

Dry Creek Facility Improvement Project Update
Just a few weeks behind the Central odor control project, the Dry Creek odor control project is expected to begin operation in September. The construction team is currently finishing work on the new biofilter treatment system.

>> View recent construction photos of all improvements at Central and Dry Creek.

Order Your Copy of our Wastewater Brochure Today!
The wastewater division of Metro Water Services has produced a brochure detailing what happens to your water once it goes down your drain to ensure that our wastewater returns to the Cumberland River clean and harmless to river ecology.

>> Order your complimentary brochure today.

We will continue to keep you updated on the progress at both Central and Dry Creek. In the meantime, please visit our Web site at www.nashville.gov/biosolids to learn more about the MWS biosolids and odor control project, and please forward this e-mail to anyone who may be interested.

Metro Water Services
1600 2nd Avenue North
Nashville, TN 37208
615-862-4600
www.nashville.gov/water




powered by emma